Cable Construction Notice
(1) Export cable pullin operations
- Vessel:Maersk Connector
- Estimated construction period:8/15-8/20
- Location:SUB A (E 120°10'15.247", N 23°42'23.322")-Wind farm YUN13 (E 120°4'0", N 23°38'34")
- Other operation vessels:Falcon 5, Hermes IV, Echo2, Echo4, Feng Neng6, Feng Neng7
(2)Cable install operations
- Vessel:Siem Topaz & Hermes IV
- Estimated construction period:8/17-8/22
- Location:SUB A (E 120°10'15.247", N 23°42'23.322")-Wind farm YUN13 (E 120°4'0", N 23°38'34")
(3)Offshore cable install operations
- Vessel:Maersk Connector(8/21-8/25)、Siem Topaz(8/22-8/26)
- Location:(120°6’0"E, 23°37'50"N) - YUN 32 ( 120°3'41" E, 23°36'22"N )