1. Update time:2023/7/6
  2. Cable Construction Notice
    (1) Inter-array cable operations
    - Vessel:Maersk Connector
    - Estimated construction period:7/11~7/15
    - Location:YUN71 (E 120° 0' 35.539", N 23° 31' 43.958") - YUN72 (E 120° 1' 3.635", N 23° 31' 48.752")
    - Other operation vessels:Boka Nothern Ocean(2) Export cable pulling operations
    - Vessel:Maersk Connector
    - Estimated construction period:7/16~7/22
    - Location:SUB A (E 120°10'15.247", N 23°42'23.322")-Wind farm YUN11 (E 120° 3' 0.322", N 23° 38' 21.034")
    - Other operation vessels: Falcon 5, Hermes IV, Echo2, Echo4, Feng Neng6, Feng Neng7

    (3)Cable install operations
    - Vessel:Siem Topaz
    - Estimated construction period:7/18-7/28
    - Location:SUB A (E 120°10'15.247", N 23°42'23.322")-Wind farm YUN11 (E 120° 3' 0.322", N 23° 38' 21.034")