- Update time:2023/7/12
- Cable Construction Notice
(1) Export cable pullin operations
- Vessel:Maersk Connector
- Estimated construction period:7/15-7/20
- Location:SUB A (E 120°10'15.247", N 23°42'23.322")-Wind farm YUN11 (E 120°3'0.322", N 23°38'21.034")
- Other operation vessels:Falcon 5, Hermes IV, Echo2, Echo4, Feng Neng6, Feng Neng7
(2)Cable install operations
- Vessel:Siem Topaz
- Estimated construction period:7/17-7/26
- Location:SUB A (E 120°10'15.247", N 23°42'23.322")-Wind farm YUN11 (E 120°3'0.322", N 23°38'21.034")