- Update time:2023/6/29
- Cable Construction Notice
(1) Export cable pullin operations
- Vessel:Maersk Connector
- Estimated construction period:7/1~7/9
- Location:SUB A (E 120°10'15.247", N 23°42'23.322")-Wind farm YUN12 (E 120° 3' 28.527", N 23° 38' 23.969")
- Other supporting vessels:Falcon 5, Hermes IV, Echo2, Echo4, Feng Neng6, Feng Neng7(2)Cable install operations
- Vessel:Siem Topaz
- Estimated construction period:7/4-7/15
- Location:SUB A (E 120°10'15.247", N 23°42'23.322")-Wind farm YUN12 (E 120° 3' 28.527", N 23° 38' 23.969")