1. Update time:2023/6/29
  2. Cable Construction Notice
    (1) Export cable pullin operations
    - Vessel:Maersk Connector
    - Estimated construction period:7/1~7/9
    - Location:SUB A (E 120°10'15.247", N 23°42'23.322")-Wind farm YUN12 (E 120° 3' 28.527", N 23° 38' 23.969")
    - Other supporting vessels:Falcon 5, Hermes IV, Echo2, Echo4, Feng Neng6, Feng Neng7

    (2)Cable install operations
    - Vessel:Siem Topaz
    - Estimated construction period:7/4-7/15
    - Location:SUB A (E 120°10'15.247", N 23°42'23.322")-Wind farm YUN12 (E 120° 3' 28.527", N 23° 38' 23.969")